Job costing supplier bills means tagging each bill line to a job so you can see cost against budget for every job.
Before you start
- Sage 200 Project Accounting
- Purchase Order Processing
- Purchase Ledger integration switched on in Project Accounting
The Sage 200 way
Where to find it: Purchase Order Processing > Purchase Orders > order line > Project Analysis
- Enter the purchase order line and fill Project and Project item in the Project Analysis section.
- Free text items: a committed cost posts to the project when you record the goods received. The actual cost posts when you record the purchase invoice, and Sage 200 adds the project analysis to the invoice itself.
- Stock items: the cost posts to the project when stock is issued to the project in Stock Control, not at the invoice. Do not enter project analysis on the invoice.
- If the confirmed stock price differs from the cost posted at issue, a Confirmed Price Adjustment transaction posts to the project.
Limits in Sage 200
- Project analysis fields only show if integration is on in Project Accounting settings.
- UK product; job costing uses the name 'project'.
The Pulsify way
- Forward the supplier's invoice to Pulsify. Pulsify reads every row as its own line.
- Review each line's account and set the job where it applies.
- Route bills to the person who knows the job, using approval rules.
- Approve. The purchase invoice is created in Sage 200 with each line.
Pulsify connects to Sage 200. We set up the connection for you.
What Pulsify does not do here
- Pulsify does not split lines by percentage.
- Job reports are run in Sage 200.
Common mistakes
- Entering project analysis on the invoice for a stock item, when the cost posts at issue.
- Filling in the Project fields on order lines without Purchase Ledger integration switched on.
More help
- How to job cost purchase invoice records in Business Central
- How to job cost bill records in MYOB Acumatica
- How to job cost A/P invoice records in Sage 300
- How to split a purchase invoice across analysis codes and cost centres in Sage 200
- How to route purchase invoice records by amount, supplier or project in Sage 200
- All Sage 200 how-to guides
- Pulsify setup guides
Sources
Last checked 2026-10-19. Confidence: confirmed.
Common questions
What do I need to job cost purchases?
Sage 200 Project Accounting and Purchase Order Processing, with Purchase Ledger integration switched on in Project Accounting. The project analysis fields only show if integration is on.
When does the cost post to the project?
For free text items a committed cost posts when you record goods received and the actual cost posts when you record the purchase invoice. For stock items it posts when stock is issued to the project.
Do I enter project analysis on stock invoices?
No. Do not enter project analysis on the invoice for stock items. If the confirmed stock price differs from the cost posted at issue, a Confirmed Price Adjustment transaction posts to the project.
Can Pulsify split by percentage?
No. Enter separate lines with set amounts.