How to job cost supplier invoice records in S/4HANA

Short answer

In S/4HANA, create each WBS element, tag each supplier invoice line with the WBS element using cost centre, WBS element and internal order and run a cost-by-WBS element report each month.

Last checked

Job costing supplier bills means tagging each bill line to a job so you can see cost against budget for every job.

Before you start

  • Project System or Controlling

The S/4HANA way

Where to find it: Manage Supplier Invoices (F0859) > G/L Account Items or PO account assignment

  1. Set the accounting object (cost centre, WBS element or order) on each G/L item.
  2. For PO items set the account assignment category Project (WBS element).
  3. Report costs from the project.

Limits in S/4HANA

  • Valuated goods receipt for project assignment needs consumption posting V in Customizing.

Words S/4HANA uses

  • Cost centre. A unit that costs are collected against, such as a team or site.
  • WBS element. A task or job code in a project structure.

The Pulsify way

  1. Forward the supplier's invoice to Pulsify. Pulsify reads every row as its own line.
  2. Review each line's account and set the job where it applies.
  3. Route bills to the person who knows the job, using approval rules.
  4. Approve. The supplier invoice is created in S/4HANA with each line.

Pulsify connects to S/4HANA. We set up the connection for you.

What Pulsify does not do here

  • Pulsify does not split lines by percentage.
  • Job reports are run in S/4HANA.

Common mistakes

  • Assigning costs to a WBS element when your company has not set up Project System or Controlling.
  • Using valuated goods receipt for project assignment without consumption posting V.

More help

Sources

Last checked 2026-10-19. Confidence: confirmed.

Common questions

How do I charge a supplier invoice to a project?

Set the accounting object (cost centre, WBS element or order) on each G/L item. For PO items set the account assignment category Project (WBS element).

What do I need switched on?

Project System or Controlling.

Is there a limit on goods receipt for projects?

Valuated goods receipt for project assignment needs consumption posting V in Customizing.

Can Pulsify split by percentage?

No. Enter separate lines with set amounts.