How to job cost vendor bill records in NetSuite

Short answer

In NetSuite, create each project, tag each vendor bill line with the project using department, class, location and project and run a cost-by-project report each month.

Last checked

Job costing supplier bills means tagging each bill line to a job so you can see cost against budget for every job.

Before you start

  • Projects enabled
  • Customer:Project on the line
  • Bill Costs To Customers feature for Billable

The NetSuite way

Where to find it: Transactions > Payables > Enter Bills > Expenses subtab (Customer column)

  1. Create the customer and project.
  2. On each bill line set the Customer:Project.
  3. Tick Billable if you pass the cost on to the customer.
  4. Open the project (Lists > Relationships > Projects > View): the Procurement subtab lists the purchase orders and vendor bills entered for it.

Limits in NetSuite

  • Bill Costs To Customers must be on to tick Billable.
  • Project vendor bill amounts exclude tax.
  • Oracle says Job Costing and Project Budgeting availability: contact your account representative.

Words NetSuite uses

  • Customer:Project. The project (job) a cost is charged to. It sits under a customer record.

The Pulsify way

  1. Forward the supplier's invoice to Pulsify. Pulsify reads every row as its own line.
  2. Review each line's account and set the job where it applies.
  3. Route bills to the person who knows the job, using approval rules.
  4. Approve. The vendor bill is created in NetSuite with each line.

Pulsify connects to NetSuite. We set up the connection for you.

What Pulsify does not do here

  • Pulsify does not split lines by percentage.
  • Job reports are run in NetSuite.

Example in NetSuite

Example Steel Supplies sends one vendor bill for $1,320.00 including GST. The amounts below are before GST.

LineAmountTagged to
Rebar for Stage 1$700.00Customer:Project: Example Client A : Stage 1
Rebar for Stage 2$500.00Customer:Project: Example Client B : Stage 2
GST 10%$120.00Tax Code on each line

Open each project and the Procurement subtab lists the bill. Project amounts exclude tax, so they show $700.00 and $500.00.

Common mistakes

  • Ticking Billable without Bill Costs To Customers turned on.
  • Reading project bill amounts as GST inclusive, when they exclude tax.

More help

Sources

Last checked 2026-10-19. Confidence: confirmed.

Common questions

How do I tie a vendor bill line to a project?

On each bill line set the Customer:Project in the Customer column of the Expenses subtab. Create the customer and project first.

Where do I see the costs for a project?

Open the project at Lists > Relationships > Projects > View. The Procurement subtab lists the purchase orders and vendor bills entered for it. Project vendor bill amounts exclude tax.

When can I tick Billable?

Bill Costs To Customers must be on. Then tick Billable on the line if you pass the cost on to the customer.

Can Pulsify split by percentage?

No. Enter separate lines with set amounts.